Aquatera Sanitary Trunk Main Phase 2
Lake Excavating Ltd. worked with engineers from Focus Corporation to complete the second phase of a sanitary main line installation in the city of Grande Prairie, AB.
Site Servicing:
- 650 m sanitary main line installation
- 1,200 mm diameter PVC installed up to 11 m deep
- Live tie-ins to the existing trunk main
- 6 2,200 mm manholes